Lawyer for Late Delivery of a New Apartment

Lawyer for Late Delivery of a New Apartment: Compensation from the Developer in Israel

A developer who did not deliver the apartment on the date in the contract must pay the buyer fixed monthly compensation under section 5A of the Sale (Apartments) Law, 5733-1973, with no need to prove damage. In contracts signed from July 7, 2022, when the delay exceeds a month, compensation is calculated from the end of the first month based on the rent of a similar apartment, and it rises in steps as the delay continues.

In short

When must a developer pay compensation for late delivery of an apartment in Israel?

Under section 5A of the Sale (Apartments) Law, in contracts signed from July 7, 2022, the developer pays when the apartment was not delivered a month after the contract date: from the end of the first month, the rent of a similar apartment; from the fifth month, 1.25 times that rent; and from the eleventh month, 1.5 times, with no need to prove damage. The developer is exempt only if it proves the delay was caused by circumstances beyond its control that it could not prevent. Do not sign a waiver as a condition for the keys before having it reviewed.

Want us to look at your case? ☎ +972-54-5427765·WhatsApp

How Much Compensation Is Due and How It Is Calculated

Compensation for late delivery is fixed by law, and there is no need to prove damage. The basis is the rent of an apartment similar to the one you bought, in size, location and standard. A contract clause that sets lower compensation is not valid, because the provisions of the Sale (Apartments) Law can be changed only in the buyer's favor.

In contracts signed from July 7, 2022, the date Amendment 9 to the law applies from, the developer pays when the apartment was not delivered a month after the contract date. There is no compensation for the first month of delay. From the end of the first month to the end of the fourth, compensation equals the rent of a similar apartment; from the fifth month to the tenth it is 1.25 times that rent; and from the eleventh month it is 1.5 times.

Older contracts follow a different rule: when the delay exceeds 60 days, compensation runs from the contract date, at 1.5 times the rent until the end of eight months and 1.25 times from the ninth month. You can estimate your amount with the late delivery compensation calculator (in Hebrew), and a full worked example appears in our guide to compensation for late delivery.

How is the rent of a similar apartment determined? Look at listings and rental deals for apartments of the same size in the same area, and in a dispute use an appraiser. The figures change over time, so document them during the delay itself, not years later when filing a claim.

Late Apartment Delivery

The Developer Blames the War, a Labor Shortage or COVID

The law allows the developer to be released from compensation when the delay was caused by circumstances beyond its control that it could not prevent. The burden of proof is on the developer. Courts examine whether it actually proved how those circumstances delayed its own project, and a general claim about the state of the economy is not enough.

So when the developer announces a postponement, ask for details in writing: what delayed the work, when and for how long. A general claim about the war, with no data about the project itself, is a starting point for negotiation, not the end of the discussion. We covered this in our update The developer is late and blames the war.

Demand Letter, Set-Off and a Claim

Start with a demand letter to the developer: the contract date, the number of months of delay, the rent of a similar apartment and the amount demanded. If the developer disputes the rent, attach an estimate from an appraiser or a real estate agent. Sometimes the letter is enough for a settlement, by payment or by set-off against the final installment.

Setting compensation off against the final installment sounds simple, but withholding payment on your own may be treated as a breach of the contract and may delay the handover of the keys. Set off only on the basis of an orderly calculation and written notice, preferably by agreement. When the developer collapsed and a receiver was appointed, the Supreme Court set special rules for set-off and for the order of payment, which we described in our update When the developer goes bankrupt.

When there is no settlement, file a claim. When several buyers in the same project are waiting for their apartments, they can sue together and share the costs of the proceedings, as we explained in a joint claim against a developer. The general limitation period is seven years, but do not wait: as time passes, it becomes harder to reconstruct the correspondence and what was promised.

A Waiver on the Day You Get the Keys

Some developers ask buyers to sign, on handover day, a document waiving every claim, including compensation for the delay, as a condition for receiving the keys. Read the document before signing. If it contains such a waiver, ask to strike it out, or write next to your signature that you sign without waiving the compensation.

A waiver signed in order to receive an apartment that was already paid for is examined by the court according to the circumstances and the rule that the law cannot be contracted out of to the buyer's detriment. But do not rely on that in advance. If the developer refuses to hand over the apartment without such a signature, consult a lawyer that same day, before you sign.

What the service includes

  • Calculating compensation by the contract signing date and the rent of a similar apartment
  • Reviewing the developer's claims of circumstances beyond its control
  • A demand letter to the developer and negotiation over payment or set-off
  • Reviewing handover documents and waivers before you sign
  • A compensation claim, including a joint claim by several buyers

When to contact us

  • The developer announced that the delivery date has been postponed
  • More than a month has passed since the contract date and the apartment was not delivered
  • The developer makes the handover of the keys conditional on signing a waiver
  • The developer refuses to pay or offers less than the law requires

What to bring to the meeting

  • The sale contract, the specification and the clause setting the delivery date
  • The developer's notices of postponement and all correspondence with it
  • Confirmations of your payments to the developer
  • The handover protocol and any documents the developer asked you to sign

Late Apartment Delivery throughout Israel

The firm represents clients from all over Israel: Jerusalem and the Shfela, Be'er Sheva, Ashdod and Ashkelon, Haifa and the North, the Sharon and Gush Dan. Meetings take place at our two Modiin branches, at the WE Towers branch in Tel Aviv or by video call, and documents can be sent in advance on WhatsApp. We represent clients in the courts, the Labor Courts and before planning committees throughout Israel. How we work with clients across Israel.

Practice area: Lawyer for Buyers of New Apartments in Israel: Late Delivery and Construction Defects

Frequently asked questions

From what date is late delivery counted?

From the delivery date set in the contract. In contracts signed from July 7, 2022, compensation is paid only when the delay exceeds a month, and it is calculated from the end of the first month. In older contracts, when the delay exceeds 60 days, compensation is calculated from the contract date itself.

The developer says the delay was caused by the war. Is it exempt from compensation?

Not automatically. The law releases the developer only when the delay was caused by circumstances beyond its control that it could not prevent, and the burden of proof is on the developer. Courts examine whether it proved how those circumstances delayed the specific project, and a general claim is not enough.

I signed a waiver to get the keys. Have I lost the compensation?

Not necessarily. The provisions of the Sale (Apartments) Law can be changed only in the buyer's favor, and a waiver signed as a condition for receiving the apartment is examined according to the circumstances. The outcome depends on the wording and on what happened on handover day, so have the document reviewed before deciding whether to sue.

Can I set the compensation off against the final payment to the developer?

Sometimes, but carefully. A set-off without an orderly calculation and written notice may be treated as a breach of the contract and may delay the handover. It is better to agree in writing on the amount and the set-off, and if there is no agreement, to have the situation reviewed before withholding a payment.

How long do I have to sue for late delivery compensation?

The general limitation period under the Prescription Law is seven years. In practice it is better to act close to the handover, while the correspondence with the developer and the evidence of the rent of a similar apartment are available.