My new apartment in Israel is delivered late. What compensation do I get?

My new apartment in Israel is delivered late. What compensation do I get?

If the developer delivers more than 60 days after the date in the contract, the Sale (Apartments) Law entitles you to monthly compensation counted from that contract date: 1.5 times the rent of a similar apartment for the first eight months, and 1.25 times from the ninth month on.

In short

If the developer delivers more than 60 days after the date in the contract, the Sale (Apartments) Law entitles you to monthly compensation counted from that contract date: 1.5 times the rent of a similar apartment for the first eight months, and 1.25 times from the ninth month on.

Want us to look at your case? ☎ +972-54-5427765·WhatsApp

What Israeli law says

Section 5A of the Sale (Apartments) Law, 5733-1973, applies when the seller has not made the apartment available to the buyer within 60 days after the delivery date set in the sale contract (the contract date). Once those 60 days pass, compensation is due for every month or part of a month from the contract date itself until delivery, not only from the 61st day. The amount is 1.5 times the rent of an apartment similar in size and location for the period ending eight months after the contract date, and 1.25 times that rent from nine months after the contract date onward, or a higher sum agreed in the contract. The compensation is paid at the end of each month, and the compensation for the first 60 days is paid when those 60 days end. The law is mandatory and cannot be waived to the buyer's detriment.

What to do now

Check the delivery date in your contract and any clause that extends it. Keep the developer's notices about the progress of construction. Once the 60 days pass, send the developer a written demand for the monthly compensation, with an estimate of the rent of comparable apartments in the area. If the developer does not pay, a claim for late delivery of a new apartment can follow.

What to watch out for

The parties may agree that the compensation will not apply to a delay caused by circumstances beyond the seller's control whose risk the seller does not bear. In a position paper of May 2021, the Sale Law supervisor at the Ministry of Construction and Housing stated that a delay caused by the conduct of a public authority, a delay caused by the seller's own contractors or advisers, and a clause that lets the seller decide by itself that a delay was beyond its control do not exempt the seller from paying. Read such clauses closely before accepting a developer's refusal to pay.

Want us to look at your case? Message us on WhatsApp

Sources

This answer is general and explains the rules. It is not legal advice and is not a substitute for a review of your own case, which depends on its own facts and documents.

Useful links

Not sure where you stand? Send us the documents and we will review them.

CallOfficeWhatsApp