Building Permit (Heter Bniya) in Israel

Building Permit (Heter Bniya) in Israel: The Licensing Process, Variances, Committee Delays and Refusal

A building permit (heter bniya) is the approval of the local licensing authority or of the local planning and building committee to carry out work that section 145 of the Planning and Building Law, 5725-1965, makes subject to a permit, including erecting a building, demolishing it and adding to an existing building. An application that conforms to the plan that applies to the plot is decided by the licensing authority, while an application that includes a variance (hakala) or a non-conforming use is published for objections and decided by the local committee. A refusal can be appealed to the district appeals committee, generally within 30 days of service of the decision.

In short

How do I get a building permit in Israel, and what if the application is refused?

A permit is required for any work that section 145 of the Planning and Building Law, 5725-1965, makes subject to a permit, including erecting a building, demolishing it and adding to an existing building. An application that conforms to the plan that applies to the plot is decided by the local licensing authority, while an application that includes a variance or a non-conforming use is published for objections and decided by the local committee. A refusal can be appealed to the district appeals committee, generally within 30 days of service of the decision.

Want us to look at your case? ☎ +972-54-5427765·WhatsApp

The Stages of a Building Permit: Permit Information, Online Filing and Design Review

Section 145 of the Planning and Building Law, 5725-1965, prohibits carrying out the works it lists without a permit, including erecting a building, demolishing it and adding to an existing building. The process begins with permit information (meida lheter): the person preparing the application, an architect or an engineer, asks the local committee for information on the plan that applies to the plot, the building rights, and the conditions and approvals that other bodies will require.

The application itself is filed in the online system known as Rishui Zamin. The committee engineer checks whether the application is complete, and under regulation 38 of the Planning and Building (Licensing of Construction) Regulations, 5776-2016, must notify the applicant of defects in the application within 10 days. After the planning approval comes design review (bakarat techen), which checks that the plans meet safety and construction requirements, at the committee itself or at a licensed review institute (machon bakara).

Before the permit is issued, the fees and levies are paid, including development levies and a betterment levy where it applies, and the conditions set in the decision are met. After the permit is issued, an approval to begin work is requested, and when construction is complete, Form 4 (tofes 4), which allows the building to be connected to electricity and water, and a completion certificate are required.

Building Permit

Who Decides: The Licensing Authority or the Local Committee, and Applications with a Variance

An application that conforms to the plan is decided by the local licensing authority. An application that includes a variance, meaning a limited departure from the provisions of the detailed plan, or a non-conforming use must be published under section 149 of the Law: in newspapers, by a notice on the front of the building or plot, and by personal notice to the owners of adjoining land, after which there are 14 days to file objections. Such an application is decided by the local committee, and section 151(a) prohibits granting a variance that amounts to a substantial deviation from the plan.

Where the application conforms to a valid plan, the committee may not replan the site at the licensing stage. In Appeal 11036-11-25, decided on January 20, 2026, the Tel Aviv District appeals committee held that the licensing authority is not authorized to engage in replanning at the licensing stage, and that it must approve an application that conforms to a valid plan, with only narrow exceptions. The position of neighbors who oppose a variance, and their side of the process, are explained on the page Objection to a Building Plan or Building Permit.

The Committee Does Not Decide, or Rejects the Application Without a Hearing

An applicant is not required to wait indefinitely. In Kiryat Ono, the local committee did not bring to a hearing, for more than a year and a half, a permit application for a neighborhood center that conformed to the plan. The appeals committee approved the application subject to conditions, held that the requirement of an approved registration map (tatzar) is a condition for issuing the permit and not a condition for hearing the application, and directed that if the local licensing authority failed to meet the deadlines, the applicant could turn to the national licensing authority. The local committee was ordered to pay costs of NIS 30,000; details in the summary of the decision (Hebrew).

A summary rejection without a hearing can also be challenged. In Fureidis, the Yishuvei HaBaron regional planning committee rejected amended permit applications without considering them on the merits. On August 6, 2024, the Haifa District appeals committee held that this was not permitted, examined the applications itself and approved them subject to amendments.

A decision to refuse an application is appealed to the district appeals committee under section 152 of the Law, generally within 30 days of the day the decision was served. Before appealing, the reasons for the refusal are reviewed, because it is sometimes faster to correct the application and file it again.

Validity of the Decision, Exempt Works and Building Without a Permit

A decision to approve a permit application is valid for a limited period, and if the conditions are not met and the payments are not made in time, it lapses. In Bat Yam, the payment vouchers for the levies and fees were served eight days before the decision expired, and with the local committee's consent the appeals committee gave effect to an arrangement under which the decision remained valid for 30 days from service of the vouchers. The expiry date should therefore be tracked from the day the decision is given.

Not every work requires a permit. The Planning and Building (Works and Structures Exempt from a Permit) Regulations, 5774-2014, exempt a closed list of works, under the conditions they set, including a pergola that meets those conditions. A work that is not on the list, or that does not meet its conditions, requires a permit.

Building without a permit exposes the owner to administrative fines, orders to stop the use and to demolish, and criminal proceedings, and it makes selling the property more difficult. A person who receives an order should check the deadlines for challenging it immediately.

What the service includes

  • Reviewing the plan that applies to the plot and the building rights before design
  • Guiding the application from permit information to issuance of the permit
  • Applications for a variance or a non-conforming use, and responses to objections
  • Approaching a committee that delays an application, and appealing when it fails to decide
  • Appeals to the district appeals committee against a refusal or permit conditions
  • Reviewing the fees, development levies and betterment levy in the payment demand

When to contact us

  • You are planning construction, an addition or a demolition and want to know what the plan allows
  • The application includes a variance, and neighbors have filed objections
  • The committee does not decide the application, or rejected it without a hearing
  • You received a payment demand or a decision with conditions, and the expiry date is approaching

What to bring to the meeting

  • A land registry extract or another document showing rights in the plot
  • The permit information received from the committee
  • The application, the plans and the decision of the committee or licensing authority
  • Payment demands, vouchers and correspondence with the committee

Building Permit throughout Israel

The firm represents clients from all over Israel: Jerusalem and the Shfela, Be'er Sheva, Ashdod and Ashkelon, Haifa and the North, the Sharon and Gush Dan. Meetings take place at our two Modiin branches, at the WE Towers branch in Tel Aviv or by video call, and documents can be sent in advance on WhatsApp. We represent clients in the courts, the Labor Courts and before planning committees throughout Israel. How we work with clients across Israel.

Practice area: Planning, Building and Betterment Levy Lawyer in Israel

Frequently asked questions

How long does it take to get a building permit in Israel?

The Law and the regulations set deadlines for the stages of handling an application, and an application with a variance or a non-conforming use takes longer because it is published and there are 14 days to file objections. In practice, the time depends on how complete the application is, on conditions set by other bodies and on design review. A committee that does not decide an application that conforms to the plan can be brought before the appeals committee, as happened in Kiryat Ono after more than a year and a half.

Who approves a building permit, the licensing authority or the local committee?

An application that conforms to the plan is decided by the local licensing authority. An application that includes a variance or a non-conforming use is published for objections and decided by the local planning and building committee.

What can I do if the local committee refused my building permit application?

Review the reasons for the refusal and the minutes. You can correct the application and file it again, or appeal to the district appeals committee under section 152 of the Planning and Building Law, generally within 30 days of the day the decision was served.

Which works are exempt from a building permit?

Only the works listed in the Planning and Building (Works and Structures Exempt from a Permit) Regulations, 5774-2014, and under the conditions they set, for example a pergola that meets those conditions. A work that is not on the list requires a permit, so the conditions should be checked before work begins.

What happens if the fees and levies are not paid in time?

The decision to approve the application is valid for a limited period, and if the conditions and payments are not completed in time it may lapse. In Bat Yam, where the vouchers were served eight days before expiry, it was agreed in the appeal that the decision would remain valid for 30 days from service of the vouchers.

Not sure where you stand? Send us the documents and we will review them.