In most cases, yes: the developer stays liable under the Sale (Apartments) Law, 5733-1973 after handover. It must repair defects found in the inspection period, one to seven years depending on the defect, and a defect visible at handover can be raised if you notify the developer within one year.
Want us to look at your case? ☎ +972-54-5427765·WhatsApp
What Israeli law says
The handover protocol (protokol mesira) records the condition of a new apartment on the day you receive it, but the developer's liability does not end there. Under the Sale (Apartments) Law, 5733-1973, as summarized by Kol Zchut, liability runs in two stages from the handover of possession. During the inspection period (tkufat bedek), which lasts from one to seven years depending on the type of defect, the developer must repair a defect unless it proves that the owner caused it. Under the schedule for apartments built in recent years, for example, leaking pipes and the sealing of the structure have four years, and cracks wider than 1.5 mm in non-load-bearing elements have five. The warranty period (tkufat achrayut) follows for three more years, and in it the buyer must prove that the defect comes from the design, the work or the materials. A defect that could have been discovered when the apartment was made available to you can be relied on if you notify the developer within one year of that date.
What to do now
Come to the handover with a home inspector or engineer and record every visible defect in the protocol, with photos. For defects you discover later, send the developer a written notice that describes each defect and demands repair, keep a copy, and give it the chance to make the repairs. If it does not repair, you may file a complaint with the Registrar of Contractors (Rasham HaKablanim) at the Ministry of Construction and Housing, or sue. More on claims against a developer: construction defects in Israel.
What to watch out for
Mark the date one year from handover: a visible defect not reported by then may be harder to claim. Some leaks appear only after the first rains, so inspect again before that date. If you are asked to sign a waiver or a no-claims statement as a condition for the keys, have it reviewed first.
Want us to look at your case? Message us on WhatsApp
Sources
This answer is general and explains the rules. It is not legal advice and is not a substitute for a review of your own case, which depends on its own facts and documents.
Useful links
- Construction Defects in New Apartments
- Buyers vs. Developers
- Can a developer link my apartment price to the construction index in Israel?
- Buying off-plan in Israel: what is the payment voucher book (pinkas shovarim)?
- My new apartment in Israel is delivered late. What compensation do I get?
- All questions and answers